By
TIM FAULKNER/ecoRI.org News staff
PORTSMOUTH
— There are three options to deal with the high school's broken wind turbine
and none of them is very promising.
The
first option, explained by town planner Gary Crosby to the Town Council on Feb.
25, is to pay up to $730,000 to replace the broken gearbox and have the town
resume ownership of the 336-foot-high turbine.
The
second option: Allow a developer to dismantle the turbine and replace it with a
new model of the same height. A private entity would own the turbine and make
lease payments to cover the $2.38 million the town owes on the project. No
additional revenue would go to the town.
“This
is just about the most complex problem I’ve ever had to face,” Crosby told the
council.
Four
developers have submitted bids for the project — two each for options 1 and 2 —
in a request for the proposals issued by the town in December.
The
first option, which Crosby described as “repair and resume,” would require the
purchase of two new gearboxes. Most new wind turbines no longer use gearboxes,
and instead rely a direct-drive system. Option 1, however, would allow the town
to receive revenue from the sale of renewable energy credits once the turbine
is operational.
After
Crosby presented the alternatives, the Town Council discussed the details in
executive session. Crosby said the council may announce its preferred option at
its meeting in March.
The
1.5-megawatt turbine was commissioned in March 2009. The turbine had a 20-year
life expectancy, but was shutdown June 18, 2012, after an inspection showed
significant wear to the gearbox. An independent investigation blamed the damage
on a faulty design. The gearbox, however, was no longer covered by warranty,
and the manufacturer of the turbine, AAER Wind Energy of Quebec, had filed for
bankruptcy. Three of five similar AAER turbines erected in California and in
Templeton, Mass., also suffered gearbox failure.
The
manufacturer of the gearboxes, Jahnel Kestermann of Germany, has offered to
sell two replacement gearboxes to the town for $203,000. It would cost the town
an additional $407,000 to remove the old gearbox and install a new one.
An
October 2012 audit (pdf) advised against the
repair-and-resume scenario. Once up and running, the turbine could deliver
annual revenue of $160,000 to the town from the sale of electricity. The
revenue, however, wouldn't be sufficient to pay the annual operating costs,
including loan payments, of some $600,000, the report concluded.