A
180-megawatt battery-storage facility has been proposed for the village of West
Kingston, R.I. (Plus Power)
By
TIM FAULKNER/ecoRI News staff
WEST
KINGSTON, R.I. — Before Rhode Island’s first utility-scale battery-storage
facility can be built, it must be decided whether the state or town has
ultimate say over the project.
At
the local level, the town of South Kingstown must figure out if the Narragansett Energy Storage
Project can be built on a 7.4-acre site that sits within a
drinking-water supply area, known as a protected groundwater overlay
district.
Forthcoming
reviews by the Rhode Island Department of Environmental Management (DEM) and
its Division of Agriculture will determine if chemicals used at the lithium-ion
battery facility pose a risk to the water supply.
Once
the opinions are received, the town will begin its review, including a public
hearing, for the project proposed on a mostly wooded site near the Kingston
train station.
The
town’s evaluation, however, may be limited if the state Energy Facility Siting
Board (EFSB) decides that the 180-megawatt project is a major energy producer.
The EFSB must approve any power plant that generates 40 megawatts or more of electricity. The question is whether the facility technically generates electricity.
The EFSB must approve any power plant that generates 40 megawatts or more of electricity. The question is whether the facility technically generates electricity.
The
developer, Plus Power, based in New York and San
Francisco, has claimed that the project isn’t a power plant, and therefore
doesn’t require EFSB review.
The
proposed facility will not generate electricity, as it will “merely store and
release electricity,” according to a document Plus Power
filed with the EFSB.
EDITOR'S NOTE: Regardless of the environmental merits of this project, this is yet another example of clearing out a large area of woods for a commercial energy project. I think the community would be much more receptive to this project if it used an old quarry, sandpit, brownfield site or closed landfill. I think the developers are aware that public opposition, a la Invenergy in Burrillville, can kill a project and will certainly jack up the costs. Location, location, location. - Will Collette
The EFSB review process is typically longer and more comprehensive than the local permitting process.
The EFSB review process is typically longer and more comprehensive than the local permitting process.
Despite
the delays for this project, battery storage is considered essential to
widespread deployment of renewable energy. Rhode Island and other states hope
to achieve climate-emission reduction goals by replacing fossil-fuel power with
thousands of megawatts of wind and solar energy.
Solar
and wind power, however, are limited by intermittency, the term that describes
gaps in electricity output when the sun isn’t shining and the wind isn’t
blowing.
Battery-storage
facilities fill those gaps by taking electricity from the grid when demand is
low and power is more plentiful. They return electricity to the system when
renewables have reduced output or during power spikes such as heat waves and
cold snaps.
Stored
power also reduces the reliance on polluting “peaker” power plants that
typically run on coal or oil and only operate during high-demand periods.
“Energy
storage technology is an important tool in the long-term health of a modern
power system,” the Rhode Island Office of Energy Resource (OER) wrote in a July 15 letter of support for excluding the
EFSB from the permitting process.
The
proposed Narragansett Energy Storage Project is made up of a series of 40-foot
shipping containers that hold inverters, transformers, and batteries that store
between 3.5 and 4.5 megawatts.
Plus
Power says the facility isn’t a power producer and loses between 5 percent and
15 percent of its energy between storage and discharge.
The
company noted that EFSB regulations don’t name energy storage as a power
generator and, despite having the opportunity to do so, the General Assembly
hasn’t classified energy storage as a power plant. Therefore, the facility
isn’t subject to the same scrutiny as a coal, natural-gas, or nuclear power
plant, according to Plus Power.
The
company said oversight and permitting for the project should be conducted by
the local zoning board, state entities such as DEM and the Coastal Resources
Management Council, and perhaps the Army Corps of Engineers. The
interconnection part of the project, however, will be reviewed by the EFSB and
ISO New England to assure that it complies with the regional electric grid.
The
Rhode Island Division of Public Utilities and Carriers (DPUC) has agreed that
the EFSB has no authority to adjudicate energy storage facilities.
In a letter to the EFSB, the DPUC says the lack
of explicit reference of energy storage in state law or by the General Assembly
means oversight of such facilities can’t be implied in the siting board’s rules.
OER
said municipalities should be allowed to decide aesthetics and setbacks from
property lines.
“Municipalities
are best suited to ensure siting and zoning ordinances for energy storage
facilities are consistent with local priorities and aligned with municipal
values,” Nick Ucci, OER’s deputy commissioner, wrote in the agency’s letter to
the EFSB.
National
Grid, which is allowed to own and operate energy-storage facilities in Rhode
Island, says it also doesn’t want the EFSB to be
the permitting entity. The state’s primary electric and gas utility agrees that
battery systems only store and release electricity.
National Grid also notes
that Massachusetts makes a distinction between energy storage and power
generation and regulates them independently.
Massachusetts,
however, has yet to rule on whether a storage facility should be approved by
the state’s energy siting board.
The
Massachusetts Energy Facilities Siting Board is currently deciding if it has jurisdiction
over the proposed 150-megawatt Cranberry Point Energy Storage Facility in
Carver, Mass. The Mass. EFSB reviews power plants that generate 150-megawatts
or more. A decision on the lithium battery storage facility is expected in the
coming months.
New
York also doesn’t declare whether energy storage is a major power producer, but
it does offer guidelines for building a facility.
Regardless
of its decision, the EFSB will review the interconnection of a substation
used by the proposed energy-storage facility. If the EFSB determines that the
project is a major energy producer, then all siting and permitting will be
decided by the three-person board.
If
built, the Narragansett Energy Storage Project would have an expected life of
20 years. But the operation would continue with the installation of new
equipment, according to Plus Power.