Menu Bar

Home           Calendar           Topics          Just Charlestown          About Us

Sunday, September 15, 2024

R.I. Chooses SouthCoast Wind to Build 200-MW Offshore Wind Facility

Bid award is part of coordinated procurement effort with Massachusetts

By Mary Lhowe / ecoRI News contributor

In the first cooperative agreement of its kind, Rhode Island and Massachusetts officials announced they would be procuring a combined 2,878 megawatts of offshore wind energy from three projects by three developers. The procurement was a result of coordinated requests for proposals (RFPs) issued last fall by Rhode Island, Massachusetts, and Connecticut.

Rhode Island selected 200 megawatts (MW) from the SouthCoast Wind project, by developer Ocean Winds, a 50-50 joint venture between EDP Renewables and ENGIE. Construction on the project is expected to start in 2025 and to deliver power by 2030.

Massachusetts selected 2,678 MW of power from three projects. They will include 1,087 MW from SouthCoast Wind; 791 MW from New England Wind 1 (formerly called Park City Wind), built by the developer Avangrid; and 800 MW from Vineyard Wind 2, built by the developer Vineyard Offshore.

For comparison, the 65 turbines of Revolution Wind, now under construction off Rhode Island’s coast, will produce 704 MW to be shared by Rhode Island and Connecticut, enough to power 350,000 homes.

Through the new procurement, offshore wind will power more than 125,000 Rhode Island homes and 1.4 million Massachusetts homes, according to state officials. One megawatt equals 1,000 kilowatts. A typical Rhode Island home uses 500 kilowatt-hours a month.

Rhode Island officials lauded the importance of the projects in creating renewable energy and reducing the use of fossil fuels. “With this project, Rhode Island is taking a significant step forward in meeting our Act on Climate goals,” Gov. Dan McKee said.

Connecticut was part of the three-state agreement to coordinate RFPs for offshore wind, but it made no announcements on Sept. 6. A spokesperson for the Connecticut Department of Energy and Environmental Protection said, “The evaluation of project bids remains under way in Connecticut and we will announce a final decision in our solicitation at a future date.”

Rhode Island and Massachusetts officials said it wasn’t feasible at this point to give information about prices and costs for the utilities and ratepayers since those are matters that will be hammered out in contract negotiations between the developers, utilities, and state regulators.

“We are limited in what information we can say as a lot of it will be subject to contract negotiations,” said Caroline Pretyman, a spokesperson for Rhode Island Energy.

Details of the SouthCoast contract, including pricing, will be open to the public when the contracts, still to be negotiated, are filed with the Rhode Island Public Utilities Commission, probably in December.

In a statement, SouthCoast said it would place its turbines at the New Bedford Marine Commerce Terminal; conduct operations and maintenance at Foss Terminal in New Bedford; and open a crew transfer and administrative hub in Rhode Island.

“SouthCoast Wind’s project represents one of the largest ever energy investments in southern New England and will revitalize Brayton Point, a former coal-fired power plant,” according to the company.

Construction is expected in late 2025, and will begin once SouthCoast has received all federal, state, and local permits, and pending final investment decision.

In answer to a question, officials said it wasn’t unusual for a developer such as SouthCoast to not have investors in place at this stage.

Rebecca Ullman, director of external affairs for SouthCoast Wind, said, “In order to secure financing, all of the project’s development risk has to be closed. The PPA [power purchase agreement] today closes a significant development risk. The final risks are the permits; SouthCoast Wind has been working on its federal, state, and local permits since 2019 and expects to finalize them in 2025. Once SouthCoast Wind has secured its permits, it will be ready to secure financing.”

Rhode Island’s selection of 200 MW of power is only one-sixth of the 1,200 MW that the state indicated it would like to obtain at the time the RFP was issued last fall.

Asked if the low amount of power that Rhode Island selected, compared to the state’s original stated intention, was a problem, an official with the Office of Energy Resources (OER) said Rhode Island Energy did a thorough review of the proposals and determined that the 200 MW “was the best opportunity” for Rhode Island. A written statement from OER said, “This selection balanced Rhode Island’s climate change objectives, renewable energy obligations, economic development opportunities, energy system benefits, and energy costs.”

Rhode Island Energy’s Pretyman said, “We collaborated … to conduct a thorough review of the proposals and decided this was the best fit for this offshore wind RFP.”

OER also said Rhode Island would be issuing another RFP for offshore wind power soon, probably in 2025. “We remain committed to pursuing additional offshore wind procurements for Rhode Island, in partnership with neighboring states, to meet our long-term goals,” according to the state agency.

During the Sept. 6 online press conference, an OER official was asked whether the state had any qualms about dealing with SouthCoast Wind because of the strained relationship between the state and the developer over the past few years.

As of early fall 2022, Southcoast Wind, originally named Mayflower Wind, had agreements with the Massachusetts Department of Public Utilities to build a 2,400-MW project to provide power to the Massachusetts grid. The turbines were slated to occupy a 199-square-mile lease area 20 miles south of Nantucket, Mass.

Part of the project would have run cables from the ocean turbines below the bottom of the Sakonnet River in Rhode Island waters. The cables would then have run underground across Portsmouth before exiting in Mount Hope Bay to meet the grid at Brayton Point in Somerset, Mass. Cables under the Sakonnet River riled fishermen and local boaters, who had no hesitation about voicing their opposition.

By mid-fall 2022, SouthCoast Wind had decided to withdraw from its power-purchase agreements with Massachusetts, claiming the project wasn’t economically viable. Around that period, a combination of inflated costs and high interest rates were putting pressure on SouthCoast and other offshore wind projects, including other projects that developers had to abandon. SouthCoast said at the time that it would bid for future contracts with better terms.

In June 2023 SouthCoast paid a penalty of $60 million to terminate the contracts. Ullman, spokesperson for SouthCoast Wind, said at the time, “Covid-related supply chain disruptions, rising interest rates, and the war in Ukraine made the contracts unfinanceable.”

In July of that year, the Rhode Island Energy Facility Siting Board (EFSB) voted to take no action on the application of SouthCoast Wind until Oct. 1 of this year or until SouthCoast obtained new financing agreements for its proposed wind project. That vote by the board also followed a prolonged kerfuffle between SouthCoast and one staff member of the Coastal Resources Management Council, along with CRMC’s Fishermen’s Advisory Board.

In August 2023, SouthCoast asked Rhode Island Supreme Court to overturn the siting board’s decision to pause consideration of its application.

On Friday, when the new procurements were announced, an OER official indicated that state officials were confident that the new relationship would work.

During the Friday press conference, Rebecca Tepper, secretary of the Massachusetts Executive Office of Energy and Environmental Affairs, offered assurances about the safety of the wind turbines in answer to a question about a blade that broke and fell in July from a Vineyard Wind turbine. Pieces of debris washed onto Nantucket and Rhode Island beaches and the incident amplified the voices of people who oppose offshore wind development.

Tepper said the blade failure was the result of a mistake during manufacturing, and “extra oversight” was being done to assure that such a mistake would not happen again. She said blades made at the same facility, either in turbines or on the ground, are all being examined for possible problems.

“Offshore wind is one of the safest forms of energy,” Tepper said. “We have had devastating problems with fossil fuel [facilities].”

All three projects intend to use project labor agreements and to create thousands of jobs and direct investments in the regional economy. All of New England’s purpose-built offshore wind ports — Port of Providence, New Bedford and Salem, Mass., and New London, Conn. — will have tenants through 2032 as a part of this selection, according to the developers and state officials. 

The SouthCoast Wind project is expected to provide 3,915 high-paying jobs in Massachusetts and Rhode Island and will invest in programs, including training partnerships with Bristol Community College/National Offshore Wind Institute and the Massachusetts Maritime Academy.

Avangrid’s New England Wind 1 project is expected to create 4,400 full-time equivalent jobs. The project will provide $130 million for the development of the offshore wind port in Salem and will locate an operations and maintenance hub in New Bedford, according to state officials. Construction could begin in 2025, with an expected operations date in 2029.

The Vineyard Wind 2 project is expected to generate 3,800 job-years of employment across New England, with 80% in Massachusetts. The project will also provide up to $37.5 million in directly funded initiatives, according to state officials. The Salem Offshore Wind Terminal will be the staging site for the project’s wind turbine installation and operations and maintenance will be done from New Bedford.

The new offshore wind facility will be the third such development with a direct relationship to Rhode Island. The Block Island Wind Farm, a 30-MW, five-turbine project built by the Danish company Ørsted and finished in 2016, was the first and, for years, the only offshore wind facility in U.S. waters.

Last fall, final approvals from federal and state agencies came through for Revolution Wind, a 65-turbine, 704-MW offshore project by Ørsted and Eversource that will supply power to Rhode Island and Connecticut. The first Revolution turbine went into the water last month, even as the company said full operations would be pushed back to 2026 from 2025 because of unexpected delays with onshore facility construction.

A bit further away, South Fork Wind, the 12-turbine project developed by Ørsted and Eversource off the end of Long Island, N.Y., began operating in March, sending up to 132 MW of electricity to New York. And Vineyard Wind, an 800-MW project of Avangrid and Copenhagen Infrastructure Partners, is being built and beginning to operate in the waters south of Martha’s Vineyard.